Five workers can manufacture 60 widgets in 6 days. Working at the same rate, how many more workers will be needed to manufacture 120 widgets in 4 days?
(A) 3
(B) 4
(C) 5
(D) 10
(E) 15
Saturday, June 13, 2009
Subscribe to:
Post Comments (Atom)
GREAT, CURRENT GMAT QUANT PROBLEMS. E-MAIL US AND WE WILL SEND YOU A PDF FILE WITH ALL PROBLEMS POSTED. GMAT and GMAC are registered trademarks of the Graduate Management Admission Council which neither sponsors nor endorses this blog.
Answer E
ReplyDeleteI think it's D -- 10 ADDITIONAL workers for a total of 15.
ReplyDeleteyou are right.....problem is asking more workers
ReplyDeleterate for 5 people is 10wpd -----(a)
ReplyDeleteso for 120w in 4 days..
you need 30 per day.
For 30 per day,
you should need 10 more people ...
Is the answer (D)...